www.achdidaho.org_ ConstructionUpdate 9-6-13
Just a few project updates from ACHD – Full list of projects and there progress attached in the link. enjoy
30th Street Extension (Fairview/State) Alta Construction $4.5 million October 2013
► Phase 1 and Phase 2 work is substantially complete.
► Crews placed curb and gutter on north side of State Street.
► Crews placed curb and gutter on the east side of Rose Street
► Placing base on the east side of 30th between Main Street and the apartments started August 26th
► The majority of the curb, gutter, sidewalk, and bottom lift of pavement are done from Jordan Street to the apartments.
36th Street, Chinden Blvd. to Waterfront Tuffy Excavation $550,000 September 2013
► All of the concrete is complete.
► Paving scheduled for next week.
► Placing brick pavers.
50th Street- Chinden Blvd. to Greenbelt WF Construction $70,000 October 2013
► All sidewalk work is complete except near irrigation improvements.
► Work on irrigation improvements is delayed until fall when irrigation water can be turned off